Central heating

GENERAL DATA FOR “TOPLOFICATION” – BRICKEL EAD

TOWN OF GULABOVO (as of 21.12.2015)

The heating system at “Brickel” EAD was built in 1989.

and entered into operation in 1990 with 24 Subscriber stations and an installed capacity of 30 MWh.

 

As of December 2022, 2090 Subscriber stations were in operation, such as:

– for private subscribers – 2011 pcs.
– for businesses and companies – 58 pcs.
– for budget enterprises – 21 pcs.

The length of the heating route is 19,400 meters.